Cleaning and removing the sands, welding slag, high temperature oxide and corrosions inside the main steam pipes and over-heater pipes of the boiler, which have been produced during manufacture, transportation,storage and installation. Prevent pipe explosion of the over-heater, damage of the turbine blades,and other serious accidents. Provide qualified steam for initiating the turbine and ensuring the safety initiation and operation.
Acceptance criteria
The cleaning is successfully completed when the target plate examination fulfills the
following criteria:
No impacts > 0.8 mm in an area of 2500 mm2
Max. 2 impacts >0.4 mm in an area of 2500 mm2
Max.10 impacts >0.2 mm in an area of 2500 mm2
Impacts < 0.2 mm2 are well dispersed and nowhere present on concentration.
Diameter indicates maximum corner to corner measurement
STEAM
BLOWING
PRINCIPLE
The activity consist of blow-up the
line with steam, discharging to the atmosphere through temporary spools and, if
possible, temporary silencers to reduce the noise into acceptable range. Steam
blowing utilizes the heat effects and kinetic energy of steam flow. Heating, blowing and cooling down of the pipe
concerned are repeated during steam blowing, this cycle of pipe expansion and
contraction together with the flow of steam removes adhering rust, weld slag,
spatter and mill scale.
The results of steam blowing are more
effective than the use of kinetic energy only as in air blowing. To obtain good
result of cleanness, the steam kinetic energy on internal of steam lines must
be higher than that we have during normal operation.
(m2xV)
MCL
where:
k =
cleaning factor
m= steam
flow (kg/s)
V= steam
specific volume (m3/kg)
SB = Steam
Blowing condition
MCL = Max
Continuous Load
For
good results during the blow up the factor K must be > 1,25
The execution of steam blowing proceeds
in the sequential order of steam supply common header, unit header, sub-header
and individual branch lines.
PRECAUTION
The following precaution is observed
while steam blowing:
1)
Before conducting any steam blowing activity, the
following matters are notified on in order to prevent boiler operational upsets
during steam blowing caused by BFW consumption and steam demand variations.
- Steam blowing schedule
- Approximate steam consumption and duration
- Actual opening and closing of the steam valve for
each steam blow
During steam blowing, it maintains close
communications between the user and producer.
2)
Steam traps shall be bypassed, or removed where
possible, at first while the upstream connecting lines are steam blown. As soon as the upstream lines are confirmed
clean, the steam traps shall be put into service and the function shall be
inspected.
3)
Check pipes are free for the expansion and have
sufficient anchorage up to the blow-off point.
4)
Sacrificial valve, such as knife valve or butterfly valve to allow quick opening, is installed at the start end of the lines,
and restriction orifice is installed downstream of such valve if required, in
order to alleviate the erosion on the valve.
5)
Steam and debris shall be blown to a safe location.
Temporary lead pipes, vents etc. shall be installed
at blow-off points as required to direct steam and debris to safe areas.
6)
The blow off area shall be cordoned off in compliance
with site safety regulations.
7)
Exposed piping shall be checked for non-contact
with combustible materials such as scaffold boards etc. to prevent the possible
outbreak of fire.
8)
Before conducting steam blowing, the pipe is slowly
warmed up in order to prevent the occurrence of steam hammer.
9)
In order to ensure effective steam blowing,
heating, blowing and cooling shall be cycled by time or temperature monitors.
10) When the
steam line is in the cool-down step or hot condensate remains, the blow-off end
must be kept open to prevent a vacuum formation inside the pipe.
11) Once
steam blowing has been successfully completed, the line instrument and line
equipment/accessories which are removed prior to steam blowing shall be
reinstated and placed in service or otherwise protected to prevent the
re-occurrence of rust.
DETAILS FOR
IMPLEMENTATION
Planning
(1) Steam
blowing shall be carried out in the sequence from upstream to downstream as
follows;
Common Header → Unit
Header → Sub
header → Branch
Lines.
After the steam blow of upstream is completed, the
downstream can be started steam blowing.
(2) Steam
blowing route shall be determined and shown on a marked up P&ID.
The following items shall be
indicated:
(a) Steam blow-off points and its timing for all blows.
(b) Major valve positions.
(c) Temporary valves, spools, lead pipes, etc.
Preparation
1) Remove
the following and upon completion reinstall:
(a) Safety valves
(b) Check valves
(c) Rupture disks
(d) Orifice plates of flow meter elements
(e) In-line
mixers/strainers
(f) Spargers
(g) Spray nozzles
(h) Control valves except ball/gate type
(i) Self-actuated control valves
except ball/gate type
(j) Emergency shut off valves
except ball/gate type
(k) All other items which could be damaged by the
ingress of dirt or restrict the blow path
(l) Steam traps,
where possible
Note: The above equipment/instrument/other
accessories, where steam blowing has been finished, can be reinstalled and used
for steam blowing of their downstream pipes as required.
2) All steam traps on lines being blown shall be bypassed at first.
3) All steam
header branch lines are closed when blowing the main header.
4) All pipe
supports related are checked and confirmed its condition.
5) Target
plates is installed and checked its position (if required).
6) Prior to
the commencement of steam blowing, the route shall be checked by Company and
Contractor personnel and confirmed at site.
Execution
Lines for steam blowing are classified
into the following groups, dependant on the requirements of the steam user:
(1) Lines
equipped with a target plate.
(2) Lines
where repeated blowing to be applied.
(3) Lines
where once-through steam blow to be applied.
Hereinafter, outlined procedures are
given for the above classifications.
Lines
Equipped with a Target Plate
This method shall be applied to steam
turbine inlet line.
(1) Warming
up
Warming up operation shall be
carried out by gradually opening the supply valve (initially using the bypass valves) and
draining all condensate from the line until dry steam is issuing from the blow
point.
(2) Blowing
Steam blowing shall be done
for a period long enough to ensure that dislodged mill scale etc. has sufficient
time to exit the pipe.
(3) Cooling
down
Cooling
down operation shall be carried out by natural or forced means dependent upon
schedule requirements.
(4) Repetition
Above procedures, (1) ~ (3),
shall be repeated three times without target.
(5) Target
plate installation
A target plate shall be
installed at the blow-off end immediately after the last steam blowing step.
(6) Final
blow or Test blow
Final blowing shall be done
with target plate for 10 minutes after warming up.
(7) Target
plate inspection
Target plate shall be removed
and inspected after the final blow.
Steam blowing shall be repeated until the
results as per the target blows are acceptable and a certificate of acceptance
is signed by the Company.
Lines
where Repeated Blowing to be Applied
The same procedure as described in
above (1) through (4) is applicable. Implementation of steam blowing for these
lines will be in the order of 10-minute blows to be repeated three times. However, blowing duration and repetition may
be considerably changed according to actual performance. This method shall be applied to lines in the
following service:
-
Heat Exchanger
-
Steam Ejector
-
Atomizer
-
Desuperheater
-
Control Valve
-
Column/Drum/Tank
-
Sparger
-
Heater for Tempered Water
-
Jacket/Coil
-
Exhaust Steam Lines of steam turbines
-
Snuffing Steam
-
Exhaust Steam Line
Lines
where Once Through Steam Blowing to be Applied
Steam blowing is carried out only
once. This method shall be applied to:
-
Steam Pipe (Header Manifold) for Steam Trace
-
Hose Station
ACCEPTANCE
CRITERIA
Acceptance criteria for steam blowing also differ
depend on the steam user classification in previous paragraph.
Lines
Equipped with a Target Plate
A copper or aluminum plate shall be
brought into contact with blown-out steam at right angles and the number and
degree of flaws formed on the plate due to the impact of foreign materials
shall be observed.
Acceptance criteria for these lines
shall be specified by the following or by equipment vendor specification: -
(1) The
number of flaws observed shall not exceed five per square centimeter.
(2) The
size of a flaw shall not exceed 0.5 mm.
Light pot-marks may be acceptable
provided that there shall be NO RAISED METAL on any penetration. Steam blowing
is deemed complete when the above criteria have been satisfied.
Lines
where Repeated Blowing will be applied
Steam blowing is deemed complete when
no dirt or debris is witnessed at the blow-off point.
Lines
where Once Through Steam Blowing will be applied
Steam blowing is deemed complete when a
single steam blowing cycle has been carried out.
POST WORK
(1) Pipes
concerned are re-installed as per P&ID immediately after steam blowing has
been completed or otherwise protected from corrosion and dirt ingress.
(2) All
completed blows are documented and recorded on P&ID's. Target plates are to be retained for
evidence.
(3) A reinstatement
work through request is conducted.
NOISE
During
steam blowing noise is one of major HSE concern. The noise produced by a steam
blow out point can to be in the region of 130-150 dB PWL. The main concerns
coming from noise are as follows:
·
Possibility
of hearing damage due to noise received by workers closed to a steam
discharging point
·
Noise
received at the nearby facilities
The
following actions can be taken to avoid the hazards due to noise:
·
Noise
source can be barricaded or cordoned off. Minimum distance is given by the
noise calculation. In these areas access shall be restricted, regardless of
whether the hearing protection is worn.
·
All
the people working in the area subject to steam blowing shall use hear protection equipment such as ear plugs and
mufflers (during the steam blowing)
·
Activity
can be performed during night time or when there is no personnel working on
site (i.e. Sunday)
·
Noise
produced can be limited by the use of silencers.
A
prediction of the expected sound generated during steam blowing is made here
below using the following formulas:
PWL=10
log (1/2 MC2η)
+120
While the sound pressure level at a
distance r from the source is calculated using this formula:
SPL = PWL – 10 log (4*π*r2)
Where:
SPL : Sound
pressure level
PWL : Sound
Power Level
r : distance
from the noise source
M : mass
flow rate (kg/sec)
C : speed
of sound of the chocked gas=kRT/Mw
k
: ratio
of specific heats (1.26 for steam)
T : Temperature
(oK)
Mw : Molecular
weight
η : Acoustic efficiency (assumed 4*10-3)
The
calculations to be made based on noise limit 115 dB (A) (See API EA 7301), and
the results give the radius of area where access shall be avoided during the
steam blowing. Based on this calculations, we can decided whether to use
silencer or not.
Tidak ada komentar:
Posting Komentar