Senin, 13 Mei 2013

Boiler Chemical Cleaning


Purpose

The purpose of boiler chemical cleaning is to remove oil/grease, rust/scaling, welding slag which is formed during boiler pressure parts fabrication. Final step of boiler chemical cleaning is to perform magnetite film layer formation on boiler tube as an indication boiler is ready to operate.

Boiler part for Chemical cleaning system

Feed water line from the feed water pumps and economizer
Water wall tube
Steam drum ¾ the volume
Super heater area not to be acid cleaning

Refractory Dry Out

Purpose

This Commissioning Procedure is provided and guide to supervise, testing and evaluation for Refractory Dry Out used base on standard and meet contract specification, and ensure that no water found at the refractory of the Boiler and system can operate normally and safely.


General Description Refractory Dry Out

This application  Combined  Low  Temperature  and  High  Temperature refractory dry-out of plant as detailed above, to the client (Refractory Manufacturers) defined temperature cycle.

Minggu, 12 Mei 2013

Panduan Komisioning GI dan Trafo

Panduan Komisioning GI dan Trafo

  • Komisioning instalasi GI merupakan rangkaian dari beberapa kegiatan pemeriksaan dan pengujian atau komisioning atas beberapa subsistemnya, yaitu:
  • Komisioning Transformator Tenaga
  • Komisioning Hubung Perlengkapan Bagi Dan Komponennya
  • Komisioning Saluran Udara Tegangan Tinggi (SUTT)
  • Komisioning Saluran Kabel Tegangan Tinggi (SKTT)
  • Komisioning Sistem Proteksi Dan Pengukuran
  • Komisioning Sistem Pembumian

Download

Panduan Komisioning PLTU

Panduan Komisioning PLTU

Komisioning instalasi Unit PLTU merupakan rangkaian dari beberapa kegiatan pemeriksaan dan pengujian atau komisioning atas beberapa subsistemnya, yaitu:
  • Komisioning Ketel Uap dan Alat Bantu
  • Komisioning Turbin Uap dan Alat Bantu
  • Komisioning Generator dan Eksitasi
  • Komisioning Bay Trafo Generator
  • Komisioning Unjuk Kerja PLTU
  • Komisioning Instalasi Listrik Bangunan lainnya

Download

Panduan Komisioning PLTP

Panduan Komisioning PLTP

Komisioning instalasi Unit PLTP dari beberapa Komisioning merupakan rangkaian kegiatan pemeriksaan dan pengujian atau komisioning atas beberapa subsistemnya, yaitu:
  • Komisioning Turbin Uap
  • Komisioning Generator dan Eksitasi
  • Komisioning Bay Trafo Generator
  • Komisioning Unjuk Kerja
  • Komisioning Instalasi Listrik Bangunan lainnya.

Download

Panduan Komisioning PLTGU

Panduan Komisioning PLTGU

  • Komisioning Unit instalasi PLTA merupakan beberapa kegiatan pemeriksaan dan beberapa subsistemnya, yaitu:
  • Komisioning Turbin Air
  • Komisioning Eksitasi Generator dan Komisioning Bay Trafo Generator
  • Komisioning Unjuk Kerja
  • Komisioning Instalasi Listrik Bangunan lainnya

Download

Panduan Komisioning PLTD

Panduan Komisioning PLTD

Komisioning instalasi Unit PLTD merupakan rangkaian dari beberapa
kegiatan pemeriksaan dan pengujian atas beberapa atau komisioning subsistemnya, yaitu:
  • Komisioning Diesel Mesin
  • Komisioning Generator dan Eksitasi
  • Komisioning Bay Trafo Generator
  • Komisioning Unjuk Kerja
  • Komisioning Bangunan lainnya Instalasi Listrik

Download